Get ready for more construction in Hoboken. Starting this April, 50 blocks of roadways in Hoboken will be repaved, with construction lasting well into June. The goals are to fix roads after major infrastructure work, upgrade crosswalks and other safety features, and improve accessibility for Hoboken locals and visitors. Here’s what to know about the repaving schedule and what streets will be closed in Hoboken.
About The Spring Repaving Project
Over two miles of roadways will be milled and repaved in Hoboken this spring and possibly summer. It adds up to about 50 blocks of streets in Hoboken getting a facelift.
Several roads in Hoboken were part of underground infrastructure improvement projects to upgrade drinking water mains, pressure valves, gas mains, and increase storm sewer capacity to reduce flooding. The City of Hoboken is working in partnership with PSE&G and North Hudson Sewerage Authority to restore these roadways following that work.
Read More: A Guide to the Coffee Shops of Hoboken
The City of Hoboken also plans to implement additional Vision Zero safety improvements during this time, such as high-visibility striping to refresh crosswalks and other roadway markings. The majority of these projects are funded through grants and utility capital projects.
“We know how frustrating it can be to drive around the city this time of year, especially after a tough winter and several construction projects that have greatly improved what’s beneath the surface, but left roads in rough condition,” said Mayor Emily Jabbour in a statement online. “These paving projects will repair many of our roadways, not only improving driving conditions, but also incorporating additional safety upgrades that support our Vision Zero goals and improve accessibility.”
What Streets Will Be Repaved?
The following streets are slated to be restored, starting in April and continuing through June. Sinatra Drive South, between First and Fourth Streets, and Hudson Place are slated to be paved later this year.
See More: 16 New North Jersey Businesses to Try This Spring
- Fifth Street from Jefferson Street to Madison Street
- Sixth Street from Grand Street to Adams Street
- Seventh Street from Grand Street to Adams Street
- Eighth Street from Grand Street to Jefferson Street
- Ninth Street from Jefferson Street to Monroe Street
- 10th Street from Jefferson Street to Madison Street
- 11th Street from Madison Street to Monroe Street
- 13th Street from Adams Street to Willow Avenue
- 14th Street from Madison Street to Clinton Street
- 15th Street from Adams Street to Park Avenue
- 16th Street from Madison to Willow Avenue
- Henderson Street from Hoboken City Boundary to Observer Highway
- Observer Highway from Hoboken City Boundary to Southwest Resiliency Park and from Harrison Street to Madison Street
- Newark Street from Madison Street to Henderson Street
- Madison Street from Newark Street to Observer Highway
- Madison Street from Fourth Street to Sixth Street, Eighth Street to 11th Street, and 13th Street to 15th Street
- Jefferson Street from Observer Highway to First Street and 13th Street to 16th Street
- Grand Street from 13th Street to 16th Street
- Clinton Street from 13th Street to 16th Street
- Adams Street from Eighth Street to Ninth Street and 15th Street to 16th Street
- Intersection of Fifth Street and Monroe Street
- Intersection of Seventh Street and Monroe Street
- Intersection of Seventh Street and Madison Street
Construction schedules are subject to change due to weather, and the City says it will provide notice prior to each roadway’s paving, such as traffic and parking impacts.
More information on repaving projects and ongoing Hoboken construction projects can be found online.
Follow @thehobokengirl on Instagram + TikTok for the latest Hoboken and Jersey City updates, sign up for our weekly newsletter here that shares everything you missed each week, and check out our events calendar, which has over 100+ events weekly to peruse.